When delivery slips, which forecast should the report question?
A late order often prompts the same explanation: the workshop was too slow. Sometimes that is true. Sometimes the promised date was already unrealistic when the quote went out. Sometimes the quote was reasonable but the production target changed later. A report that only labels an order late cannot tell these stories apart. For a manager, the useful question is not simply whether a number is red, but which estimate should be challenged.
Imagine an illustrative workshop, not a customer case. It has completed several orders this period, and one missed its delivery date. At the meeting, everyone immediately discusses overtime. Before that discussion, someone ought to ask what date was promised to the customer, what date production was working towards and when the order was actually delivered. Those are distinct moments. Collapsing them into one label makes it harder to find a practical correction.
Decide what period the screen describes
The General tab of infab.cloud’s Reporting screen lets a manager choose a date range, defaulting to the beginning of the current month through today. Its cards include counts of quotes and orders, planned work hours and hours estimated at the quotation stage. Cancelled quotes and orders are excluded from these counts. The workshop employee count is different: it shows the current total regardless of the selected date range. That detail matters when several cards sit together on one screen.
At the start of a review, name the date range and the population under discussion. Dividing last month’s quotes by today’s employee count will not suddenly produce a sound historical productivity measure just because both values are nearby. A filter does not turn every figure on the screen into a historical snapshot. Each card has a source event and a time meaning. Those meanings need to remain visible when somebody carries the figures into a meeting or a spreadsheet.
A delivery rate starts a question; it does not answer it
The On Time Delivery Rate card looks at delivered orders and asks what proportion were delivered on or before the target date. A Delivery Performance summary also separates on-time and late deliveries and shows average delay in days. The documented target-date rule uses the date promised to the customer first. If that is missing, the production-stage estimated date is used. That precedence is easy to overlook when somebody assumes every delivery was judged against an identical kind of promise.
If the rate falls in our hypothetical workshop, do not jump straight to “the floor needs to work faster.” First check what each late order was measured against. Was there a customer promise? Did the production target differ? Did several misses cluster around a particular planning period or operation? The aggregate points to a set of records worth examining. It does not establish the cause of any one delay.
A healthy-looking rate also has boundaries. The proportion is based on orders that have been delivered. It is not a forecast of what will happen to open orders. If the selected period has few completed deliveries, one number can be a weak description of the work still in progress. Keep the denominator in mind before presenting the card as an overall verdict on all promises currently in the system.
Separate a sales estimate from a production target
The Forecast Accuracy summary makes a useful distinction. It shows the deviation of the estimate made at the quotation stage and, separately, the deviation of the target set during production, both in days. The reporting interface tests also check that these two lines appear independently. This is not a shortcut to assigning blame. It is a way to decide which assumptions deserve an inspection.
If the quotation-stage estimate repeatedly misses, examine how lead times and effort were assessed before the order was accepted. If the production-stage target drifts more, inspect scheduling, available capacity and the order in which work was released. Those are questions suggested by the split, not automated diagnoses supplied by the software. Compare the figures to the underlying order before attributing a delay to any person, shift or machine.
The General tab also distinguishes planned work hours from hours estimated in the quote. They are useful context when a team asks how the work was imagined before acceptance and how it was planned after release. Neither hours card proves why a delivery date was missed. Together with the two forecast deviations, however, they offer a more disciplined starting point than a broad accusation that production fell behind. Ask what changed between estimating the job and planning it, then look for a record that explains the change.
Other reports answer other questions
Reporting has more than a General tab. Machine Reports has machine-level utilisation and efficiency metrics. The Efficiency tab calculates daily efficiency from finished quantities entered through the workshop screen and can group the results by operation or worker. Only work sessions with a finished quantity entered are counted. An operation with no planned duration appears as having no plan. The documented daily grouping uses UTC, a detail worth checking when comparing days around a reporting boundary.
Do not use one of these figures as an automatic explanation for another. A delivery can be late even when a particular operation shows strong efficiency. Missing quantity entries may also reduce the number of work sessions represented in the efficiency view. The tabs address different questions: whether a delivery met its target, which forecast missed and how recorded output compares with planned time. Treating them as interchangeable does not simplify the analysis; it strips the numbers of their meaning.
A modest trial is more useful than a grand dashboard review. Pick one completed order. Put the customer-facing date, production target and actual delivery alongside one another from its records. Select the matching period in the General tab and look at the delivery and forecast summaries. If the answer seems surprising, check the date definition and filter before proposing a process change. Then ask whether planned hours changed between the quote and the released work. This gives the meeting a specific record to discuss rather than an abstract argument about percentages.
A delivery metric earns its place when it helps identify the decision that should be revisited. infab.cloud outlines the production approach, while the reporting documentation defines these views in detail. The distinction between a promised date and a later production target is a useful place to begin your own review.