A purchase suggestion is not stock you can use
The floor is waiting for material. Purchasing has raised an order, and some of it has already arrived. Yet the planner still cannot answer a simple question: can we issue it to the job today? Ordered, physically received and available for production describe three different states. Treating them as synonyms turns a seemingly settled purchasing task into a surprise at the machine.
Consider a hypothetical workshop, not a customer account. An open work order needs sheet material. The same material has fallen below its configured replenishment threshold. Purchasing places an order, but the supplier delivers only part of it. The incoming quantity is awaiting inspection. Several things have moved forward, yet none of those facts alone tells the planner how much approved material can be issued. The useful record is the chain between demand, supplier order, receipt and quality decision.
Why the suggestion appeared matters
infab.cloud documents two sources for purchase suggestions. A material with a manually configured reorder point can trigger one when its stock balance falls below that threshold. An open work order can trigger another if the material required by its recipe lines exceeds the current stock balance. They are different signals: one reflects a stocking rule, the other an actual open production requirement. The application does not turn either signal into a supplier commitment without a person selecting and creating a draft purchase order.
A missing reorder point does not mean the material will never show up in a work order driven suggestion. Conversely, seeing both reasons for the same material does not mean you should simply add their proposed quantities together. You could buy twice for the same shortage. Check existing orders, the current balance and the production requirement before deciding on a quantity. The software can surface reasons; it cannot negotiate a delivery or decide how much buffer your operation should carry.
For work order demand, there may also be a date. Where an operation has a scheduled date and the material has a lead time, the code derives a latest order date by working backwards from the operation date. That is a planning calculation, not a confirmed supplier delivery date. If the schedule changes, the date’s meaning changes with it. A threshold suggestion has no specific operation date to work back from. When reviewing a list of alerts, ask which inputs support each date rather than treating every highlighted item as equally urgent.
A draft order is not a receipt
Selected suggestions can be converted to draft purchase orders grouped by supplier. The buyer still needs to check the supplier, quantity, unit price and currency. The application gives a purchase order its own number and tracks its state from draft through sent and confirmed, then partially received or received as deliveries are recorded. Cancellation is a separate state. Those stages tell the team what has happened; none implies that a lorry has arrived merely because the order was confirmed.
In the example, the first partial delivery increases the received quantity on the order line. The order becomes partially received. The receiving endpoint rejects a quantity that would push the line beyond the ordered amount. Once every line is fully received, the order becomes received. That header status is useful for understanding the supplier order as a whole, but it is not a certificate that all material has passed inspection or is safe to release to production.
Receiving a line creates an inbound stock movement with the purchase order as its source and document reference. The movement starts with incoming quality status pending. Under the documented stock rule, only incoming movements that have passed quality count towards the usable balance. This is the crucial gap between “it arrived” and “the floor can use it.” If the operation has more than one warehouse, the receiving flow also allows the destination warehouse to be specified. Checking a global number without checking where material was received can leave a planner with the wrong practical answer.
Keep three decisions separate
Purchasing asks what to order. The warehouse records what has physically arrived. The incoming quality process determines what counts as usable stock. In the hypothetical workshop, the open work order suggestion does not prove that an order was sent. A partial receipt does not guarantee when the remainder will arrive. A pending quality receipt does not fill today’s available quantity. A planning discussion should show each amount and state explicitly rather than reduce the whole chain to “material available.”
There is a related workflow in the same Purchasing area that answers a different question. A material check request asks the warehouse what is actually ready for a particular order before production starts. The warehouse can answer available, partially available, unavailable or propose an alternative. That conversation does not create a purchase order just because the answer is unavailable. We covered how that request affects an order’s recipe in the earlier material check article. A purchase suggestion, by contrast, is a planning signal derived from a threshold or work order demand. They may concern the same material without being interchangeable records.
To test the process in a controlled way, start with one material. Check whether it has a reorder point, what an open work order actually needs, and whether there is already an open supplier order. Review the suggestion before creating a draft. Record a partial receipt and inspect both the order state and the resulting inbound movement. Finally, look at the movement’s quality state before calling the material available to the floor. This sequence will expose the point where your team currently jumps from a purchasing intention to a production promise.
The order is not complete just because somebody clicked the last button in Purchasing. What matters is whether the team can explain which quantity was requested, which quantity arrived and which quantity has passed the incoming gate. For a broader view of the product, see infab.cloud; the documented steps for suggestions, orders and receiving are in the purchasing guide.
Verification note: This article was checked against the infab.cloud purchasing and rules documentation, the purchase order API implementation and its tests. The workshop example is illustrative, not a customer case.